10 Variation Payment Dates Previously Declared Special Charge Schemes PDF 125 KB
Minutes:
SUMMARY
Council at its meeting 11 April 2023 resolved that Council consider a report at a future meeting prior to 1 July 2023 to modify the payment dates for seven Special Charge Schemes that will proceed to construction but will not begin delivery when the Special Charge Scheme is due to be levied on 1 July 2023.
This report recommends modifying the commencement of landowner payment dates from 1 July 2023 to 1 July 2024 for the following (referred as the seven Special Charge Schemes):
· Alpine Street, Cecil Street and Glenbrook Road, Warburton
· Welham Road, Mooroolbark - Bretby Way, Montrose
· Emery Lane Montrose
· Alfred Street and John Street, Wandin North
· Tainton Street and Railway Parade, Wandin North
· Cedar Court, Burns Way (includes Harvest Close), Loch Avenue and Mayview Drive, Monbulk
·
Moved: Cr Skelton That Council 1. Modify the landowner payment dates for seven Special Charge Schemes from 1 July 2023 until 1 July 2033 to 1 July 2024 until July 2034 as the road construction will not commence before charges are due to be levied. (a) Alpine Street, Cecil Street and Glenbrook Road, Warburton. (b) Welham Road, Mooroolbark. (c) Bretby Way, Montrose. (d) Emery Lane, Montrose. (e) Alfred Street and John Street, Wandin North. (f) Tainton Street and Railway Parade, Wandin North. (g) Cedar Court, Burns Way (includes Harvest Close), Loch Avenue and Mayview Drive, Monbulk. 3. Notify those persons liable to pay the special charge of the modification of payment dates for the Special Charge Scheme and provide new instalment arrangements. The motion was Carried unanimously. |